Installation Guides for Curve Ceiling Board

1.Direction of Bending

The orientation of the reinforcing fiber is in parallel along the long side of the board. The best bending direction should be in parallel to the reinforcing fiber ( i.e. parallel to the long sides. )

2.Application of Water

  • Method A
    The board should be placed horizontally and water is applied to the board by hose spraying or other means.
    It should be allowed to absorb water for at least 15 mins. until the board saturated with water.

  • Method B
    Immense the board into shallow pool of water made by vinyl sheet or others means and allow the board to the saturated for 9-10 mins.

3 Bending

Saturated board is bent by pressing it slowly to the pre-shaped suspension frame. During the boards is bending, attention have to pay for any crack appears. If so happens, this means that the board is not saturated and water should be applied again.

For bending the board in small radius (around 100mm), a molding have to use for the board bending instead of bending at the suspension at the suspension frame. Make sure that the board must saturated with water. )

4.Board Fixing

Fixing of board is by means of using countersunk head screws ( dia. 7 x 20mm ) at 250-300mmm c/c along the suspension system.

curve9_p.jpg (15864 bytes)
Curve10_p.jpg (22440 bytes)
Curve11_p.jpg (28917 bytes)

5.Minimum Radius for Curve Ceiling Board

Thickness Min. radius without water Min. radius with water
5mm 1.5m 150mm
6mm 2.0m 200mm

6.Dry out Period

  Under normal circumstances, saturated board takes 3 to 4 days to dry out. This mean that other decorative finishes are
  not recommended to apply until 4 days later.

7.Precautions